DOMINO CONSTRUCTION UPDATE:Week of January 19th, 2015 and January 26th, 2015

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the site.

The work crew is beginning to remove debris from the upland site (Site E) as part of the pre-construction site prep.  A construction fence is planned to be installed around the perimeter of Site E towards the end of February.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of January 5th, 2015 and January 12th, 2015

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the Site.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of December 22nd, 2014 and December 29th, 2014

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the Site.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of December 8th, 2014 and December 15, 2014

Mechanical demolition of the Building 16 tower has been completed. Demolition is currently paused at the Boiler House while asbestos abatement activities are underway inside the stacks. Sorting and grading activities are ongoing throughout the Site. Support beams were installed on several structural steel beams at the Raw Sugar Warehouse as additional support.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of November 24th, 2014 and December 1, 2014

Sorting, grading, and cleaning activities are ongoing at the Raw Sugar Warehouse. Mechanical demolition of the Boiler House continues – workers were demolishing the building’s exterior bin structure. Hand demolition is ongoing at Building 16. Workers aided by a man-lift break brick away from the exterior at the top of the building.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of November 10th, 2014 and November 17, 2014

Demolition activities concluded at the Raw Sugar Warehouse and Sorting, grading, and cleaning activities are ongoing at the Raw Sugar Warehouse.The structural steel frame along the East River remains to be used for the construction of an elevated public park. Sorting, grading, and cleaning activities are continuing at the site. Mechanical demolition of the Boiler House is ongoing. An excavator with a long-reach attachment demolishes the building from the north side. Hand demolition is ongoing at Building 16. All of the non-structural steel has been removed from the building. Workers aided by a man-lift are breaking brick away from the exterior at the top of the building. A geotechnical investigation is underway at Site E.

Posted in Construction Updates | Tagged , ,

DOMINO CONSTRUCTION UPDATE:Week of October 27 , 2014 and November 3, 2014

Demolition activities are ongoing at the Raw Sugar Warehouse. Hand demolition is continuing on the west side of the building along the East River. Mechanical demolition continues on the south and north sides of the building. Skidsteers sort demolition debris outside of the Raw Sugar Warehouse along its eastern side.

Mechanical demolition of the Boiler House is ongoing. Hand demolition is ongoing inside Building 16.

Posted in Construction Updates