DOMINO CONSTRUCTION UPDATE:Week of February 16th, 2015 and February 23rd, 2015

Mobilization for construction has begun at “Site E”. Temporary orange barriers were installed along South 3rd and South 4th Streets. Temporary parking signs are currently posted until official signage is received from the DOT. Soot removal and asbestos abatement are ongoing inside the Boiler House stacks. Mechanical demolition will resume in the next 2 weeks.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of February 2nd, 2015 and February 9th, 2015

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the site.

Site E is imminently going to begin construction. Mobilization onsite and the construction  fence will begin on the 16th of February.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of January 19th, 2015 and January 26th, 2015

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the site.

The work crew is beginning to remove debris from the upland site (Site E) as part of the pre-construction site prep.  A construction fence is planned to be installed around the perimeter of Site E towards the end of February.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of January 5th, 2015 and January 12th, 2015

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the Site.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of December 22nd, 2014 and December 29th, 2014

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the Site.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of December 8th, 2014 and December 15, 2014

Mechanical demolition of the Building 16 tower has been completed. Demolition is currently paused at the Boiler House while asbestos abatement activities are underway inside the stacks. Sorting and grading activities are ongoing throughout the Site. Support beams were installed on several structural steel beams at the Raw Sugar Warehouse as additional support.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of November 24th, 2014 and December 1, 2014

Sorting, grading, and cleaning activities are ongoing at the Raw Sugar Warehouse. Mechanical demolition of the Boiler House continues – workers were demolishing the building’s exterior bin structure. Hand demolition is ongoing at Building 16. Workers aided by a man-lift break brick away from the exterior at the top of the building.

Posted in Construction Updates