DOMINO CONSTRUCTION UPDATE:Week of September 8, 2014 and September 15, 2014

The Boiler House is undergoing Phase III mechanical demolition work. A hydraulic excavator is installed along the north side of the Boiler House to demolish the upper floors. Excavators and skidsteers sort the demolition debris which is stockpiled on the site of the former Building 16/Adant House. Workers aided by a man-lift flame-cut steel from the roof on the western side of the Boiler House. The four remaining sugar tanks located at the southern side of the building were removed and stored near the southern edge of the property. Mechanical demolition of the south side of the Boiler House is ongoing.

The “Domino Sugar” sign is in the process of being taken down from the west side of Building 16. Several of the letters have been removed. Workers are constructing cradles around each of the letters for storage. Hand demolition has begun inside the Building 16 tower where workers are flame-cutting metal.

Grading was completed on the site of the former Building 16/Adant House as well as the former vegetated field located east of the Raw Sugar Warehouse.

The Raw Sugar Warehouse is undergoing preparation for demolition. Extension of the perimeter fence along Grand Street towards the East River was completed. The windows were removed from the building. Workers are cleaning sugar from the building interior.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of August 25, 2014 and September 1, 2014

The Boiler House is undergoing Phase III mechanical demolition work. Excavators are located along the north side of the Boiler House to demolish the building’s upper floors. Excavators and skidsteers are sorting the demolition debris which was then removed to stockpiles located on site. Workers aided by a man-lift are flame-cutting steel from the roof on the western side of the Boiler House.

Building 16 is undergoing preparation for the removal of the Domino Sugar sign and demolition of the remaining portions of the building. The emergency hoist system was completed and successfully passed a drop test. Hand demolition of the Domino Sugar sign and the remaining portion of Building 16 will begin shortly.

Excavation and removal of the two (2) underground storage tanks located in the vegetated field was completed. The process of re-grading the area is ongoing.

The perimeter fence along Grand Street is undergoing extension towards the East River in preparation for the demolition of the Raw Sugar Warehouse.

Posted in Uncategorized

DOMINO CONSTRUCTION UPDATE:Week of August 11, 2014 and August 18, 2014

The Boiler House is undergoing Phase III mechanical demolition work. Excavators are staging construction debris along the north side of the building.On the west side of the Boiler House, workers aided by a man-lift are flame cutting steel from the exterior.

Building 16 is undergoing preparation for the removal of the Domino Sugar sign and demolition of the remaining portions of the building. Holes were cut into the north side of the structure to allow installation of a hoist. Scaffolding was erected on the west side of the structure.

The two underground storage tanks located in the vegetated field are undergoing excavation and removal. Excavators were moving soil and sorting metal debris.

Posted in Uncategorized

DOMINO CONSTRUCTION UPDATE:Week of July 28, 2014 and August 4, 2014

The Boiler House is undergoing Phase III mechanical demolition work. Machinery demolished and sorted metal on the north side of the Boiler House. On the south side of the Boiler House, workers aided by basket cranes flame cut steel from the exterior stacks. A dunnage was assembled on the south side of the property, where Building 15 had been formerly located. The four remaining sugar tank towers will be moved from the south side of the Boiler House and stored on the dunnage so that the surrounding area can be demolished.

Building 16 is undergoing preparation for the removal of the Domino Sugar sign and demolition of the remaining portions of the building. Holes were cut into the north side of the structure to erect a hoist system. Scaffolding materials are stored on the west side of the structure and will be erected once the hoist is assembled.

The cleanup of the two underground storage tanks and associated piping located in the vegetated field has been completed. The tanks and piping are awaiting removal.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: July 14, 2014 and July 21, 2014

The Boiler House is undergoing Phase III hand demolition work. Separation of the north side of the Boiler House from The Refinery is ongoing. Workers aided by two basket cranes are flame cutting steel from stacks located on the south side of the Boiler House.

The two remaining bridges between Building 16 and The Refinery were disconnected and removed from the Site. Cleaning of the two underground storage tanks has been completed. Asbestos abatement activities are ongoing in the Raw Sugar Warehouse.

Posted in Construction Updates | Tagged , ,

DOMINO CONSTRUCTION UPDATE: June 30, 2014 and July 7, 2014

The Boiler House is undergoing Phase III hand demolition work. Separation of the north side of the Boiler House from The Refinery is ongoing. Workers completed hand demolition of an interior brick wall adjacent to The Refinery and have progressed further with the demolition of the concrete slab. Removal of the concrete slab on the two remaining bridges between Building 16 and The Refinery was completed; workers are currently flame cutting and removing the bridges’ non-structural steel.

The underground storage tanks on the northeast corner of the site are continuing to be cleaned and removed from site.

The Creative Time – Kara Walker exhibit has been closed. Thanks for visiting!

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: June 16, 2014 and June 23, 2014

Hand demolition of Boiler building is on-going.

Cleaning of underground storage tanks has begun. 

Posted in Construction Updates | Tagged ,