DOMINO CONSTRUCTION UPDATE:Week of August 25, 2014 and September 1, 2014
The Boiler House is undergoing Phase III mechanical demolition work. Excavators are located along the north side of the Boiler House to demolish the building’s upper floors. Excavators and skidsteers are sorting the demolition debris which was then removed to … Continue reading