DOMINO CONSTRUCTION UPDATE: Weeks of October 28th, November 4th, and November 11th, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete, except for the commercial hoist area of the commercial tower, which will remain open into the next calendar year. Interior fit outs have been completed in the residential leg of the building and continue in the commercial leg and the bridge. The South First roadway and sidewalk have been poured and are now accessible to the public. The Grand Street sidewalk has been poured and will remain behind a construction gate until the commercial lobby is opened. The residential leasing office is now open between 10 am and 7 pm. Residential lobby has been completed and is being utilized by residents. Commercial lobby is expected to open late November. There are TCOs are in place and move in’s of the lower residential floors are occurring between 8 am and 5 pm. The commercial leasing team is beginning their leasing efforts.

The Refinery shoring work is complete. This consists of steel structures on the exterior to brace the existing brick façade during demolition. Interior demolition has begun, and currently is on the 6th floor of the building, working their way downward.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of October 14th and October 21st, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete except for the commercial hoist area of the commercial tower. The remaining work will be completed in 2 shifts, one during daytime and a second from 3-10 pm. Interior fit outs have been completed in the residential leg of the building and continue in the commercial leg and the bridge. The South First roadway and sidewalk have been poured and are now accessible to the public. The Grand Street sidewalk has been poured and will remain behind a construction gate until the commercial lobby is opened. The residential leasing office is now open between 10 am and 7 pm. Residential lobby has been completed and is being utilized by residents. Commercial lobby is expected to open early November. There are TCOs are in place and move in’s of the lower residential floors are occurring between 8 am and 5 pm.

The Refinery shoring work is complete. This consists of steel structures on the exterior to brace the existing brick façade during demolition. Interior demolition has begun, and currently is on the 7th floor of the building, working their way downward.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 30th and October 7th, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete except for the commercial hoist area of the commercial tower. The remaining work will be completed in 2 shifts, one during daytime and a second from 3-10 pm. Interior fit outs have begun and framing and sheet rocking are working their way up the building. The South first roadway and sidewalk have been poured. The Grand Street sidewalk is expected to be poured within the next week. The residential leasing office is now open between 10 am and 7 pm. Residential lobby has been completed. Commercial lobby is expected to open early November. The TCOs are in place and move in’s of the lower residential floors are occurring between 8 am and 5 pm.

The Refinery shoring work is complete. This consists of steel structures on the exterior to brace the existing brick façade during demolition. Interior demolition has begun, and currently is on the 7th floor of the building, working their way downward.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 9th and September 16th, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue their overhead, riser and fit out work. Precast Facade erection is complete except for the commercial hoist area. The remaining work will be completed in 2 shifts, one during daytime and a second from 3-10 pm. Interior fit outs have begun and framing and sheet rocking are working their way up the building. The South first Street sidewalk is set to be poured mid September, with the road opening around the same time. The Grand Street sidewalk will be poured in late September. The residential leasing office is now open, with a TUP and TPP in place. Residential lobby to be completed within the next week. The TCOs are expected to be in place by the end of the month.

The Refinery shoring work is complete. This consists of steel structures on the exterior to brace the existing brick façade during demolition. Interior demolition has begun, and currently is on the 8th floor of the building, working their way downward.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of August 26th and September 2nd, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue their overhead, riser and fit out work. Precast Facade erection is complete except for the commercial hoist area. The remaining work will be completed in 2 shifts, one during daytime and a second from 3-10 pm. Interior fit outs have begun and framing and sheet rocking are working their way up the building. Kent Ave sidewalk is complete. South first street sidewalk will be poured mid September, with the road opening around the same time. Grand Street sidewalk will be poured mid to late September. Residential leasing office is now open, with a TUP and TPP in place. Residential lobby to be completed within the next 2 weeks. Inspections for future TCOs are being scheduled.

The Refinery shoring work is complete. This consists of steel structures on the exterior to brace the existing brick façade during demolition. Interior demolition has begun, and currently is on the 10th floor of the building, working their way down the building.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 15th and April 22nd, 2019

At Site A the ground floor through 42nd floor slabs are complete. We will be pouring the bulkhead slabs during these weeks. Topping out of the building is scheduled for April 24th, this will conclude the concrete pouring operations. stripping, grinding and cleanup will continue for the next 2 weeks. MEP trades will continue their overhead, riser and firout work. Precast Facade erection will work 2 shifts, one during daytime and a second from 3-10 pm. The facade is wrapping the building from bottom up and is curently on the 28th floor. Interior fitouts have begun and framing and sheet rocking are on the 14th floor and working their way up the building. Sidewalk and ground floor facade work will begin in the next 2 weeks

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition. The southern and northern towers are complete. Work on the west side of the structure is complete.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 1st and April 8th, 2019

At Site A the ground floor through 37th floor slabs are complete. We will be pouring the 38th, 39th floor slab during these weeks. Topping out of the building is scheduled for April 24th. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun and will framing and sheet rocking on the 14th floor and working their way up the building. Sidewalk and ground floor facade work will begin in the next 2 weeks

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition. The southern and northern towers are complete. Work on the west side of the structure has begun

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates