DOMINO CONSTRUCTION UPDATE: Week of May 15th, 2017 and May 22nd, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is nearly complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of May 1st, 2017 and May 8th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is nearly complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 17th, 2017 and April 24th, 2017

Construction of our park has begun, including earthwork and the marine platform deck. Our precast bulkhead work is nearly complete. Relocation all the syrup tanks and gantry crane bases are completed. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical and plumbing work has begun.

The new bulkhead and seawall system is substantially complete, punchlist items remain. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is COMPLETE. All MEP trades are doing riser and horizontal work. Installation of CMU, exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 3rd, 2017 and April 10th, 2017

Construction of our park has begun, including earthwork and the marine platform deck. Our precast bulkhead work is nearly complete. Relocation all the syrup tanks and gantry crane bases are completed. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical and plumbing work has begun.

The new bulkhead and seawall system is substantially complete, punchlist items remain. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is COMPLETE. All MEP trades are doing riser and horizontal work. Installation of CMU, exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of March 20th, 2017 and March 27th, 2017

Construction of our park has begun, including earthwork and the marine platform deck. Our precast bulkhead work is nearly complete. Relocation of 3 of the 4 syrup tanks and gantry cranes is completed. Layout and construction of SMU planter walls and the western perimeter wall has begun. Trenching and installation of street utilities has also begun.

The new sea wall is near completed. And 90% of the marine deck is completed. All other trades will begin mobilizing in the coming weeks. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is COMPLETE. All MEP trades are doing riser and horizontal work. Installation of CMU, exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of March 6th, 2017 and March 13th, 2017

Construction of our park has begun, including earthwork and the marine platform deck. By the 2nd week of March our precast bulkhead work will be complete. Relocation of the site artifacts will begin in the coming weeks.

The new sea wall is near completely installed. And 70% of the marine deck is completed. All other trades will begin mobilizing in the coming weeks. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is COMPLETE. All MEP trades are doing riser and horizontal work. Installation of CMU, exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of February 20th, 2017 and February 27th, 2017

Construction of our park has begun, including earthwork and the marine platform deck. By the 2nd week of March our precast bulkhead work will be complete. Relocation of the site artifacts will begin in the coming weeks.

The new sea wall is near completely installed. And 70% of the marine deck is completed. All other trades will begin mobilizing in the coming weeks. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is COMPLETE. All MEP trades are doing riser and horizontal work. Installation of CMU, exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

 

Posted in Construction Updates