DOMINO CONSTRUCTION UPDATE: Weeks of April 15th and April 22nd, 2019

At Site A the ground floor through 42nd floor slabs are complete. We will be pouring the bulkhead slabs during these weeks. Topping out of the building is scheduled for April 24th, this will conclude the concrete pouring operations. stripping, grinding and cleanup will continue for the next 2 weeks. MEP trades will continue their overhead, riser and firout work. Precast Facade erection will work 2 shifts, one during daytime and a second from 3-10 pm. The facade is wrapping the building from bottom up and is curently on the 28th floor. Interior fitouts have begun and framing and sheet rocking are on the 14th floor and working their way up the building. Sidewalk and ground floor facade work will begin in the next 2 weeks

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition. The southern and northern towers are complete. Work on the west side of the structure is complete.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 1st and April 8th, 2019

At Site A the ground floor through 37th floor slabs are complete. We will be pouring the 38th, 39th floor slab during these weeks. Topping out of the building is scheduled for April 24th. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun and will framing and sheet rocking on the 14th floor and working their way up the building. Sidewalk and ground floor facade work will begin in the next 2 weeks

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition. The southern and northern towers are complete. Work on the west side of the structure has begun

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of March 18th and March 25th, 2019

At Site A the ground floor through 35rd floor slabs are complete. We will be pouring the 36th , 37th & 38th floor slab during these weeks. Topping out of the building is scheduled for the end of April. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will framing and sheet rocking on the 12th floor and working their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition. The southern and northern towers are complete. Work is to begin on the west side of the structure shortly.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of March 4th and March 11th, 2019

At Site A the ground floor through 33rd floor slabs are complete. We will be pouring the 34th & 35th floor slab during these weeks. Topping out of the building is scheduled for the end of April. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will framing and sheet rocking on the 10th floor and working their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of February 18th and February 25th, 2019

At Site A the ground floor through 33rd floor slabs are complete. We will be pouring the 34th & 35th floor slab during these weeks. Topping out of the building is scheduled for the end of April. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will framing and sheet rocking on the 10th floor and working their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of February 4th and February 11th, 2019

At Site A the ground floor through 28th floor slabs are complete. We will be pouring the 29th & 30th floor slab during these weeks. We have schedule a crane jump for the 9th and 10th. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will work their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of January 21st and January 28th, 2019

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Framing and rebar above the bridge has begun. We will be pouring the 28th floor slab the week of the 28th and frame the 29th. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will work their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates