DOMINO CONSTRUCTION UPDATE: Week of August 7th, 2017 and August 14th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts has begun. Erection of the gantry cranes is complete and work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are mostly completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the first TCO. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

At Site A we have broken ground! Excavation, SOE and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of July 24th, 2017 and July 31st, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, Mechanical and plumbing work has begun. The elevated walk steel is complete and painting of the artifacts has begun. Erection of the gantry cranes is complete and work is progressing from the north end to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are being built out and apartment fit out has begun. Final inspections throughout the building are completed for the first TCO. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

At Site A we have broken ground! Excavation, SOE and dewatering work has begun. Digging is continuing daily and production pile installation has begun.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of July 10th, 2017 and July 17th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is complete and painting of the artifacts has begun. Erection of the gantry cranes is complete and work in progressing from north to south on the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fit out has begun. Final inspections throughout the building are completed for the first TCO. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue will be open to the public shortly.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of June 26th, 2017 and July 3rd, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fit out has begun. Final inspections throughout the building are scheduled in the next month.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of June 12th, 2017 and June 19th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fit out has begun. Final inspections throughout the building are scheduled in the next month.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of May 29th, 2017 and June 5th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is nearly complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fit out has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of May 15th, 2017 and May 22nd, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is nearly complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates