DOMINO CONSTRUCTION UPDATE: Weeks of October 29th and November 5th, 2018

At Site A the ground floor through 15th floor commercial and 20th floor Residential slabs are complete. The commercial 16, 17 & 18 and residential 21, 22 and 23rd floor slabs will be complete by 11/9 .  There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the following few weeks. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade will be complete on the residential tower up to the 11th floor by the end of October and then will continue up the building on the interior of the “O” in the building.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of October 15th and October 22nd, 2018

At Site A the ground floor through 13th floor commercial and 16th floor Residential slabs are complete. The commercial 14 &15 and residential 17, 18 and 19th floor slabs will be complete by 10/26 .  There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the following few weeks. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade will be complete on the residential tower up to the 11th floor by the end of October.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of October 1st and October 8th, 2018

At Site A the ground floor through 10th floor commercial and 13th floor Residential slabs are complete. The commercial 11,12 & 13 and residential 14, 15 and 16th floor slabs will be complete by 10/12 .  There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the following few weeks. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection has begun on a second shift and will end prior to 10pm every evening. They will be complete on the residential tower up to the 11th floor by the end of October.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 17th and September 24th, 2018

At Site A the ground floor through 10th floor slabs are complete. The 11th and 12th Floor concrete should be completed by 9/30. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be doing cable pulls equipment through September which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection has begun on a second shift and will end prior to 10pm every evening.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 3rd and September 10th, 2018

 

At Site A the ground floor through 8th floor slabs are complete. The 9th and 10th Floor concrete should be completed by 9/7. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be doing cable pulls equipment the beginning of September which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection has begun on a second shift and will end prior to 10pm every evening.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of August 20th and August 27th, 2018

At Site A the ground floor through 6th floor slabs are complete. The 7th and 8th Floor concrete should be completed by 9/7. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be doing cable pulls equipment the beginning of September which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection has begun on a second shift and will end prior to 10pm every evening.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of July 30th, August 6th and August 13th, 2018

At Site A the ground floor through 5th floor slabs are complete. The 6th floor concrete should be completed by 8/22. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be doing cable pulls equipment later in August which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection is set to begin August 20th

 

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street

 

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates