DOMINO CONSTRUCTION UPDATE: Week of November 27th, 2017 and December 4th, 2017

At Site A  Excavation, SOE, pile driving and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and are continuing to be installed. Underground plumbing work has begun.

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts only needs touchup work. Pavers and precast planks have been delivered to site and are being installed. Finishes including light fixtures, handrails and millwork has begun. Construction of the new road is underway. Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing roughing and final installation. Installation of exterior cladding is nearly complete & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the South tower. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of November 13th, 2017 and November 20th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts is nearly complete. Pavers and precast planks have been delivered to site and are being installed. Finishes including light fixtures, handrails and millwork has begun. Construction of the new road is underway. Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing roughing and final installation. Installation of exterior cladding is nearly complete & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the South tower. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

At Site A  Excavation, SOE, pile driving and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and are continuing to be installed.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of October 30th, 2017 and November 6th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts is nearly complete. Pavers and precast planks have been delivered to site and are being installed. Finishes including light fixtures, handrails and millwork has begun. Construction of the new road is underway. Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing roughing and final installation. Installation of exterior cladding is nearly complete & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are mostly completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the South tower. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

At Site A  Excavation, SOE, pile driving and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of October 16th, 2017 and October 23rd, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts is nearly complete. Pavers and precast planks have been delivered to site and are being installed. Finishes including light fixtures, handrails and millwork has begun. Construction of the new road is underway. Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing roughing and final installation. Installation of exterior cladding is nearly complete & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are mostly completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the South tower. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

At Site A  Excavation, SOE, pile driving and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of October 2nd, 2017 and October 9th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts has begun. Pavers and precast planks have been delivered to site. Construction of the new road is underway. Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are mostly completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the first TCO. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

At Site A  Excavation, SOE and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of September 18th, 2017 and September 25th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts has begun. We are expecting pavers and precast plank work to be delivered by the end of September. Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are mostly completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the first TCO. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

At Site A  Excavation, SOE and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of September 4th, 2017 and September 11th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts has begun. We are expecting pavers and precast plank work to be delivered by the end of September. Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are mostly completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the first TCO. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.

At Site A we have broken ground! Excavation, SOE and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun.

Posted in Construction Updates