DOMINO CONSTRUCTION UPDATE: Weeks of May 28, June 4, & June 11.

At Site A the ground floor and 2nd floor slab are complete. The 3rd floor concrete should be completed by 6/22. The Con-Ed vaults will be installed on Kent Ave this will reroute bike and pedestrian traffic for 3-4 weeks. Sidewalk shed is erected. MEP trades have begun their overhead and in deck work. Curtainwall erection is set to begin in August.

Construction of the Domino Park is nearly complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 30, May 7 & May 14, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Ground Floor Slab and foundation walls for Site A are complete. Underground plumbing and electric work is complete. Superstructure Concrete has mobilized and pouring of the first section of 2nd floor columns and slab has begun. The Con-Ed vaults will be installed on Kent Ave has begun this will reroute bike and pedestrian traffic for 3-4 weeks. Sidewalk shed is being erected.

Construction of the Domino Park is nearly complete. Electrical, Mechanical and Plumbing work is ongoing and nearly complete. Finishes including light fixtures, handrails and millwork is nearly complete. Paving of the new road had begun. The food kiosk construction is underway. Opening of the park is tentatively schedule for the beginning of June.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run is complete. Hoist run apartments are complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 16th, 2018 and April 23rd, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Slab on grade and foundation walls for Site A are complete. Underground plumbing and electric work is complete. Superstructure Concrete has mobilized and pouring of the first section of ground floor slab has occurred and is continuing daily. The tower crane has been erected. The Con-Ed vaults will be installed on Kent Ave has begun this will reroute bike and pedestrian traffic for 3-4 weeks.

Construction of the Domino Park is ongoing, concrete sidewalk, pavers, railings and finish work. Electrical, Mechanical and plumbing work is ongoing and nearly complete. Pavers and precast planks have been delivered to site and are installed. Finishes including light fixtures, handrails and millwork is nearly complete. Paving of the new road had begun. The food kiosk construction is underway. Opening of the park is tentatively schedule for the beginning of June.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run is complete. Hoist run apartments are nearly complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018

At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. Underground plumbing and electric work is complete. Superstructure Concrete has mobilized and pouring of the first section of ground floor slab will be the week of 4/2. The tower crane has been erected. The Con-Ed vaults will be installed on Kent Ave at the beginning of April, this will reroute bike and pedestrian traffic for 3-4 weeks.

Construction of the Domino Park is ongoing, concrete sidewalk, pavers, railings and finish work. Electrical, Mechanical and plumbing work is ongoing and nearly complete. Pavers and precast planks have been delivered to site and are installed. Finishes including light fixtures, handrails and millwork has begun. Paving of the new road had begun. The food kiosk construction is underway. Opening of the park is tentatively schedule for the end of May.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run is nearly complete. Hoist run apartments are nearly complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of March 19th, 2018 and March 26th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 weeks. The underground garage structure has been completed. Underground plumbing and electric work has begun. Superstructure Concrete has mobilized. Tower crane will be erected on March23-25th. The Con-Ed vaults will be installed on Kent Ave at the end of March, this will potentially reroute bike and pedestrian traffic for 3-4 weeks.

Construction of the Domino Park is ongoing, concrete sidewalk, pavers, railings and finish work. Electrical, Mechanical and plumbing work is ongoing. Pavers and precast planks have been delivered to site and are installed. Finishes including light fixtures, handrails and millwork has begun. Paving of the new road had begun. The food kiosk construction is underway Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run has begun immediately after. Hoist run apartments are finishing fitout. Mechanical rooms are completed and apartment fit out is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of March 5th, 2018 and March 12th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 weeks. The underground garage structure has been completed. Underground plumbing and electric work has begun. Superstructure Concrete has mobilized. Tower crane will be erected on March23-25th. The Con-Ed vaults will be installed on Kent Ave at the end of March, this will potentially reroute bike and pedestrian traffic for 3-4 weeks.

Construction of the Domino Park is ongoing, concrete sidewalk, pavers, railings and finish work. Electrical, Mechanical and plumbing work is ongoing. Pavers and precast planks have been delivered to site and are installed. Finishes including light fixtures, handrails and millwork has begun. Paving of the new road had begun. The food kiosk construction is underway Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run has begun immediately after. Hoist run apartments are finishing fitout. Mechanical rooms are completed and apartment fit out is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of February 19th, 2018 and February 26th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete.Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A will be installed over the next month The underground structure has been completed. Underground plumbing and electric work has begun. Superstructure Concrete is set to mobilize in March. Tower crane erection has begun. Starting in March the Con-Ed vaults will be installed on Kent Ave, this will potentiall reroute bike and pedestrian traffic for 3-4 weeks.

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts only needs touchup work. Pavers and precast planks have been delivered to site and are installed. Finishes including light fixtures, handrails and millwork has begun. Paving of the new road had begun. The food kiosk construction is underway Work is progressing from the north to the southern end of the site.

The public park located on Site C is open 6 days a week.

At Site E, the northern hoist has been removed and cladding of the hoist run has begun immediately after. Hoist run apartments are finishing fitout. Mechanical rooms are completed and apartment fit out is complete.

Posted in Construction Updates