DOMINO CONSTRUCTION UPDATE:Week of May 30th, 2016 and June 6th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the 8th floor slab on the south tower and supporting columns are being poured daily. All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work has begun.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of May 16th, 2016 and May 23rd, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the 7th floor slab on the south tower and supporting columns are being poured daily. All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work has begun.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of May 2nd, 2016 and May 9th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the 6th floor slab on the south tower and supporting columns are being poured daily. All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work has begun.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of April 18th, 2016 and April 25th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the 5th floor slab and supporting columns are being poured daily. All MEP trades have mobilized and have begun deck work and coordination efforts.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of April 4th, 2016 and April 11th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the 4th floor slab and supporting columns are being poured daily. All MEP trades have mobilized and have begun deck work and coordination efforts.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of March 7th, 2016 and March 14th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete has begun and sections of the 2nd floor slab and supporting columns are being poured daily. All MEP trades have mobilized and have begun deck work and coordination efforts

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of January 25th, 2015 and February 1st, 2015

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. They are continuing to remove metal piers from the River.  The public park located on Site C is open 6 days a week.

At Site E superstructure concrete has begun and the first section of slab had been poured. All MEP trades have mobilized and have begun deck work.

Posted in Construction Updates