DOMINO CONSTRUCTION UPDATE: Weeks of February 4th and February 11th, 2019

At Site A the ground floor through 28th floor slabs are complete. We will be pouring the 29th & 30th floor slab during these weeks. We have schedule a crane jump for the 9th and 10th. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will work their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of January 21st and January 28th, 2019

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Framing and rebar above the bridge has begun. We will be pouring the 28th floor slab the week of the 28th and frame the 29th. MEP trades will continue their overhead, riser and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will work their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of January 7th and January 14th, 2018

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Framing and rebar above the bridge has begun. This is a lengthy process and are expecting to pour the slabs at the end of the month. Utility work in the street on Kent avenue  is mostly complete with gas work wrapping up in the spring. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. Interior fitouts have begun on the 5th floor and will work their way up the building.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of December 24th and December 31st, 2018

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Utility work in the street on Kent avenue  is mostly complete with gas work wrapping up in the spring. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up. The precast planks should be installed and grouting, rebar and formwork for the connecting beams and slabs will begin. The site will be closed 12/24,12/25, 12/31 & 1/1.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of December 10th and December 17th, 2018

At Site A the ground floor through 22th floor commercial and 27th floor Residential slabs are complete. Utility work in the street on Kent avenue  is mostly complete with gas work wrapping up in the spring. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up and currently the push is to complete the interior “O” façade before the precast planks are installed. The week of 12/17 the precast planks which connect the residential and commercial towers are being installed. It will be 3 days of deliveries and setting the planks follow by a few days of grouting. Once complete, concrete operations will continue above.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of November 26th and December 3rd, 2018

At Site A the ground floor through 20th floor commercial and 26th floor Residential slabs are complete. There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the coming few weeks. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up and currently the push is to complete the interior “O” façade before the precast planks are installed.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The Refinery shoring work has begun. This will consist of steel structures on the exterior to brace the existing brick façade during demolition.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of November 12th and November 19th, 2018

At Site A the ground floor through 18th floor commercial and 23th floor Residential slabs are complete. There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the coming few weeks. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Precast Facade erection has begun on a second shift and will end prior to 10pm every evening. The facade is wrapping the building from bottom up.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates