DOMINO CONSTRUCTION UPDATE:Week of April 4th, 2016 and April 11th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the 4th floor slab and supporting columns are being poured daily. All MEP trades have mobilized and have begun deck work and coordination efforts.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of March 7th, 2016 and March 14th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete has begun and sections of the 2nd floor slab and supporting columns are being poured daily. All MEP trades have mobilized and have begun deck work and coordination efforts

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of January 25th, 2015 and February 1st, 2015

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. They are continuing to remove metal piers from the River.  The public park located on Site C is open 6 days a week.

At Site E superstructure concrete has begun and the first section of slab had been poured. All MEP trades have mobilized and have begun deck work.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of January 11th, 2015 and January 18th, 2015

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River.  The public park located on Site C is open 6 days a week.

At Site E underground utilities in conjunction with foundation wall shot-crete work is Completed. Superstructure concrete is beginning imminently and all MEP trades are onboard and will mobilize shortly as well.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of December 28th, 2015 and January 4th, 2015

These are slow weeks due to the Holiday, hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River.  The public park located on Site C is open 6 days a week.

At Site E underground utilities in conjunction with foundation wall shot-crete work is continuing with the foundation concrete pad completed.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of December 14th, 2015 and December 21st, 2015

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River.  The public park located on Site C is open 6 days a week.

At Site E underground utilities in conjunction with foundation wall shot-crete work is continuing with the foundation concrete pad completed.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of November 30th, 2015 and December 7th, 2015

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River.  The public park located on Site C is open 6 days a week.

At Site E underground utilities in conjunction with foundation wall shot-crete work is continuing with the foundation concrete pad completed.

Posted in Construction Updates