Author Archives: ttmcdomino

DOMINO CONSTRUCTION UPDATE: Week of October 2nd, 2017 and October 9th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of September 18th, 2017 and September 25th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of September 4th, 2017 and September 11th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of August 21st, 2017 and August 28th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of August 7th, 2017 and August 14th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of July 24th, 2017 and July 31st, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, Mechanical and plumbing work has begun. The elevated walk steel is complete and painting … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of July 10th, 2017 and July 17th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel … Continue reading

Posted in Construction Updates