DOMINO CONSTRUCTION UPDATE: Weeks of February 10th, 2020 and February 17th, 2020

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg and the residential bridge; the fit out work in the … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of January 27th and February 3rd, 2020

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg and the residential bridge; the fit out work in the … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of January 13th and January 20th, 2020

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg and the residential bridge. Precast Facade erection is complete, except … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of December 30th 2019 and January 6th, 2020

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg and the residential bridge. Precast Facade erection is complete, except … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of December 16th and December 23rd, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete, except for the commercial hoist area of the commercial … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of December 2nd and December 9th, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete, except for the commercial hoist area of the commercial … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of November 18th and November 25th, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete, except for the commercial hoist area of the commercial … Continue reading

Posted in Construction Updates