Author Archives: ttmcdomino

DOMINO CONSTRUCTION UPDATE: Week of February 5th, 2018 and February 12th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete.Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A will be installed over … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is complete and production piles along with tie back installation is complete. Foundation footings have been poured and are … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of January 8th, 2018 and January 15th, 2018

At Site A  Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation is complete. Foundation footings have been poured and … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of December 25th, 2017 and January 1st, 2018

At Site A  Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of December 11th, 2017 and December 18th, 2017

At Site A  Excavation, SOE, pile driving and dewatering work is ongoing. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and are continuing to be … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of November 27th, 2017 and December 4th, 2017

At Site A  Excavation, SOE, pile driving and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and are continuing to be … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of November 13th, 2017 and November 20th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting … Continue reading

Posted in Construction Updates