Author Archives: ttmcdomino

DOMINO CONSTRUCTION UPDATE: Week of November 27th, 2017 and December 4th, 2017

At Site A  Excavation, SOE, pile driving and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. Foundation footings have been poured and are continuing to be … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of November 13th, 2017 and November 20th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of October 30th, 2017 and November 6th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of October 16th, 2017 and October 23rd, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is complete and the western perimeter wall is complete. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of October 2nd, 2017 and October 9th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of September 18th, 2017 and September 25th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of September 4th, 2017 and September 11th, 2017

Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is … Continue reading

Posted in Construction Updates