Monthly Archives: December 2014

DOMINO CONSTRUCTION UPDATE:Week of December 22nd, 2014 and December 29th, 2014

Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the Site.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of December 8th, 2014 and December 15, 2014

Mechanical demolition of the Building 16 tower has been completed. Demolition is currently paused at the Boiler House while asbestos abatement activities are underway inside the stacks. Sorting and grading activities are ongoing throughout the Site. Support beams were installed … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of November 24th, 2014 and December 1, 2014

Sorting, grading, and cleaning activities are ongoing at the Raw Sugar Warehouse. Mechanical demolition of the Boiler House continues – workers were demolishing the building’s exterior bin structure. Hand demolition is ongoing at Building 16. Workers aided by a man-lift break … Continue reading

Posted in Construction Updates