Category Archives: Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of July 30th, August 6th and August 13th, 2018

At Site A the ground floor through 5th floor slabs are complete. The 6th floor concrete should be completed by 8/22. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of July 16th and July 23rd, 2018

At Site A the ground floor through 3rd floor slabs are complete. The 4th floor concrete should be completed by 8/3. The Con-Ed vaults are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of June 18th, June 25th, July 2nd, and July 9th, 2018

At Site A the ground floor through 3rd floor slabs are complete. The 4th floor concrete should be completed by 7/23. The Con-Ed vaults are installed on Kent Ave , the bike lane has been returned to the curb however ConEd … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of May 28th, June 4th, and June 11th, 2018

At Site A the ground floor and 2nd floor slab are complete. The 3rd floor concrete should be completed by 6/22. The Con-Ed vaults will be installed on Kent Ave this will reroute bike and pedestrian traffic for 3-4 weeks. … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 30th, May 7th, and May 14th, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Ground Floor Slab and foundation walls for Site A are complete. Underground plumbing and electric work is complete. Superstructure Concrete has mobilized and pouring of the first … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 16th, 2018 and April 23rd, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Slab on grade and foundation walls for Site A are complete. Underground plumbing and electric work is complete. Superstructure Concrete has mobilized and pouring of the first … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018

At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. Underground plumbing and electric work is complete. … Continue reading

Posted in Construction Updates