Category Archives: Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of May 28, June 4, & June 11.

At Site A the ground floor and 2nd floor slab are complete. The 3rd floor concrete should be completed by 6/22. The Con-Ed vaults will be installed on Kent Ave this will reroute bike and pedestrian traffic for 3-4 weeks. … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 30, May 7 & May 14, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Ground Floor Slab and foundation walls for Site A are complete. Underground plumbing and electric work is complete. Superstructure Concrete has mobilized and pouring of the first … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 16th, 2018 and April 23rd, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Slab on grade and foundation walls for Site A are complete. Underground plumbing and electric work is complete. Superstructure Concrete has mobilized and pouring of the first … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018

At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. Underground plumbing and electric work is complete. … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of March 19th, 2018 and March 26th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of March 5th, 2018 and March 12th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of February 19th, 2018 and February 26th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete.Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A will be installed over … Continue reading

Posted in Construction Updates