Category Archives: Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of October 14th and October 21st, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete except for the commercial hoist area of the commercial … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 30th and October 7th, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work. Precast Facade erection is complete except for the commercial hoist area of the commercial … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 9th and September 16th, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue their overhead, riser and fit out work. Precast Facade erection is complete except for the commercial hoist … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of August 26th and September 2nd, 2019

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue their overhead, riser and fit out work. Precast Facade erection is complete except for the commercial hoist … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 15th and April 22nd, 2019

At Site A the ground floor through 42nd floor slabs are complete. We will be pouring the bulkhead slabs during these weeks. Topping out of the building is scheduled for April 24th, this will conclude the concrete pouring operations. stripping, … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 1st and April 8th, 2019

At Site A the ground floor through 37th floor slabs are complete. We will be pouring the 38th, 39th floor slab during these weeks. Topping out of the building is scheduled for April 24th. MEP trades will continue their overhead, riser … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of March 18th and March 25th, 2019

At Site A the ground floor through 35rd floor slabs are complete. We will be pouring the 36th , 37th & 38th floor slab during these weeks. Topping out of the building is scheduled for the end of April. MEP trades … Continue reading

Posted in Construction Updates