Category Archives: Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of May 18th, 2020 and May 25th, 2020

At Site A all major façade work is complete. All remaining work, minor in its nature, has been halted due to Coronaviris. Lobbies on Grand St and South First St remain open. Sidewalks are installed on Kent Avenue, South First … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of May 4th, 2020 and May 11th, 2020

At Site A all major façade work is complete. All remaining work, minor in its nature, has been halted due to Coronaviris. Lobbies on Grand St and South First St remain open. Sidewalks are installed on Kent Avenue, South First … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 20th, 2020 and April 27th, 2020

At Site A all major façade work is complete. All remaining work, minor in its nature, has been halted due to Coronaviris. Lobbies on Grand St and South First St remain open. Sidewalks are installed on Kent Avenue, South First … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 6th, 2020 and April 13th, 2020

At Site A all major façade work is complete; work that remains is minor: caulking, finishing, and glass replacement as needed. MEP trades has halted their work on interior fit outs in the commercial leg of the tower in the … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of March 23rd, 2020 and March 30th, 2020

At Site A all major façade work is complete- currently working on caulking, finishing, and glass replacement as needed. MEP trades to continue work on interior fit outs in the hoist line apartments and commercial leg of the tower. Lobbies … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of March 9th, 2020 and March 16th, 2020

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg. Precast Facade erection is complete, except for the commercial hoist … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of February 24th, 2020 and March 2nd, 2020

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg and the residential bridge; the fit out work in the … Continue reading

Posted in Construction Updates