DOMINO CONSTRUCTION UPDATE:Week of October 5th, 2015 and October 12th, 2015
Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the south end of the Site is ongoing. they are removing removing metal piers from the River. A concrete cutting & coring company isĀ on … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE:Week of October 5th, 2015 and October 12th, 2015