DOMINO CONSTRUCTION UPDATE:Week of November 16th, 2015 and November 23rd, 2015
Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River. A concrete cutting & coring company isĀ on site to … Continue reading
Posted in Construction Updates