Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is … Continue reading