DOMINO CONSTRUCTION UPDATE: Weeks of September 17th and September 24th, 2018

At Site A the ground floor through 10th floor slabs are complete. The 11th and 12th Floor concrete should be completed by 9/30. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the … Continue reading