-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 16 AND FEBRUARY 23
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 2 AND FEBRUARY 9
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 19 AND JANUARY 26
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 5 AND JANUARY 12
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 22 AND DECEMBER 29
Daily Archives: September 6, 2019
DOMINO CONSTRUCTION UPDATE: Weeks of September 9th and September 16th, 2019
At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue their overhead, riser and fit out work. Precast Facade erection is complete except for the commercial hoist … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of September 9th and September 16th, 2019