Monthly Archives: March 2020

DOMINO CONSTRUCTION UPDATE: Weeks of March 23rd, 2020 and March 30th, 2020

At Site A all major fa├žade work is complete- currently working on caulking, finishing, and glass replacement as needed. MEP trades to continue work on interior fit outs in the hoist line apartments and commercial leg of the tower. Lobbies … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of March 9th, 2020 and March 16th, 2020

At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue fit out work in the commercial leg. Precast Facade erection is complete, except for the commercial hoist … Continue reading

Posted in Construction Updates