-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 9 AND NOVEMBER 16
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 26 AND NOVEMBER 2
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 12 AND OCTOBER 19
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 28 AND OCTOBER 5
- DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 14 AND SEPTEMBER 21
Monthly Archives: June 2020
DOMINO CONSTRUCTION UPDATE: Weeks of June 15th, 2020 and June 22nd, 2020
At Site A all major façade work is complete. All remaining work, minor in its nature, has been halted due to Coronaviris. Lobbies on Grand St and South First St remain open. Sidewalks are installed on Kent Avenue, South First … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of June 15th, 2020 and June 22nd, 2020