Monthly Archives: August 2023

DOMINO CONSTRUCTION UPDATE- WEEKS OF JULY 24 AND JULY 31

Tower Cranes have been erected and are active daily at both Site D and the Refinery.  Concrete superstructure and Steel Erection is complete at the Refinery, all Exterior steel shoring towers have been removed, and all façade masonry work is … Continue reading

Posted in Construction Updates | Comments Off on DOMINO CONSTRUCTION UPDATE- WEEKS OF JULY 24 AND JULY 31