DOMINO CONSTRUCTION UPDATE- WEEKS OF JUNE 12 AND JUNE 19

Tower Cranes have been erected and are active daily at both Site D and the Refinery.  Concrete superstructure and Steel Erection is complete at the Refinery, all Exterior steel shoring towers have been removed, and all façade masonry work is … Continue reading