DOMINO CONSTRUCTION UPDATE- WEEKS OF MARCH 4 AND MARCH 11

Tower Crane has been erected and is active daily at Site D. Concrete superstructure and steel erection is complete at the Refinery and all façade masonry work is complete. Interior construction of the Refinery is underway and glass installation is ongoing. Site B is fenced off and is used for Refinery construction staging. A separate portion of site B is accessible off river street containing Domino Park bathrooms and
staffing/operations. Construction of Domino Park, Site E and Site A is complete. All superstructure work at Site D is now complete. Tower facade installation work is underway. Interior construction is underway within Site D. Above grade work at site C has commenced.


Public entrances to Domino Park are on Grand St, South 1st St, and South 5th St.

This entry was posted in Construction Updates. Bookmark the permalink.