Tower Crane has been erected and is active daily at Site D. Concrete superstructure and steel erection is complete at the Refinery and all façade masonry work is complete. Interior construction of the Refinery is underway and glass installation is ongoing. Site B is fenced off and is used for Refinery construction staging. A separate portion of site B is accessible off river street containing Domino Park bathrooms and staffing/operations. Construction of Domino Park, Site E and Site A is complete. All superstructure work at Site D is now complete. Tower facade installation work is complete with the exception of the hoist line areas. Interior construction is underway within Site D. Above grade work at site C has commenced.
Public entrances to Domino Park are on Grand St, South 1st St, and South 5th St.
-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 8 AND DECEMBER 15
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 24 AND DECEMBER 1
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 10 AND NOVEMBER 17
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 27 AND NOVEMBER 3
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 13 AND OCTOBER 20