DOMINO CONSTRUCTION UPDATE- WEEKS OF JUNE 17 AND JUNE 24

Concrete superstructure and steel erection is complete at the Refinery and all façade masonry work is complete. Interior construction of the Refinery is underway and glass installation is ongoing. Site B is fenced off and is used for Refinery construction … Continue reading