Exterior construction of the Refinery is complete. Interior construction of the Refinery is underway. Site B is fenced off and is used for Refinery construction staging. Construction of Domino Park, Site E and Site A is complete. All superstructure work at Site D is complete. Tower facade installation work is complete with the exception of the south tower hoist line areas. South tower hoist has been removed and infill is underway. Interior construction is underway within Site D, with the lower tower floors now occupied. Above grade work at site C has commenced and is expected to be completed Fall 2024.
Public entrances to Domino Park are on Grand St, South 1st St, South 2nd Street, South 3rd Street, and South 5th St. Public Restrooms have been relocated to the Refinery with an entrance on S 3rd Street.