Exterior construction of the Refinery is complete. Interior construction of the Refinery is underway. Site B is fenced off and is used for Refinery construction staging. Construction of Domino Park, Site E and Site A is complete. All superstructure work at Site D is complete. Tower facade installation work is complete with the exception of the south tower hoist line areas. South tower hoist has been removed and infill is underway. Interior construction is underway within Site D, with the lower tower floors now occupied. Site C (Domino Square) is now complete with the exception of the interior retail spaces- the public plaza is now open.
Public entrances to Domino Park are on Grand St, South 1st St, South 2nd St, South 3rd St, South 4th Street, and South 5th St. Public Restrooms have been relocated to the Refinery with an entrance on S 3rd St.