DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 16 AND DECEMBER 23
All sites at Domino, with the exception of site B, are now completed or have interior ongoing work only. Construction of Domino Park, Site E and Site A is complete. Exterior construction of the Refinery and Site D is complete. … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 16 AND DECEMBER 23