Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 16 AND FEBRUARY 23
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 2 AND FEBRUARY 9
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 19 AND JANUARY 26
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 5 AND JANUARY 12
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 22 AND DECEMBER 29
February 2025 M T W T F S S 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Monthly Archives: February 2025
DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 17 AND FEBRUARY 24
All sites at Domino, with the exception of site B, are now completed or have interior ongoing work only. Construction of Domino Park, Site E and Site A is complete. Exterior construction of the Refinery and Site D is complete. … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 17 AND FEBRUARY 24