DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 24 AND DECEMBER 1
Excavation has commenced at Site B, with foundation work underway. The site is fenced off on all streets. All sites at Domino, with the exception of site B, are now completed or have interior work only remaining. Construction of Domino … Continue reading
Posted in Construction Updates