Recent Posts
May 2026 M T W T F S S 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Author Archives: ttmcdomino
DOMINO CONSTRUCTION UPDATE: Week of January 8th, 2018 and January 15th, 2018
At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation is complete. Foundation footings have been poured and … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of January 8th, 2018 and January 15th, 2018