DOMINO CONSTRUCTION UPDATE: Weeks of September 9th and September 16th, 2019
At Site A the ground floor through 42nd floor slabs are complete. The bulkheads for the building are complete. MEP trades will continue their overhead, riser and fit out work. Precast Facade erection is complete except for the commercial hoist … Continue reading