Category Archives: Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of October 1st and October 8th, 2018

At Site A the ground floor through 10th floor commercial and 13th floor Residential slabs are complete. The commercial 11,12 & 13 and residential 14, 15 and 16th floor slabs will be complete by 10/12 .  There will be water, … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 17th and September 24th, 2018

At Site A the ground floor through 10th floor slabs are complete. The 11th and 12th Floor concrete should be completed by 9/30. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 3rd and September 10th, 2018

  At Site A the ground floor through 8th floor slabs are complete. The 9th and 10th Floor concrete should be completed by 9/7. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of August 20th and August 27th, 2018

At Site A the ground floor through 6th floor slabs are complete. The 7th and 8th Floor concrete should be completed by 9/7. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of July 30th, August 6th and August 13th, 2018

At Site A the ground floor through 5th floor slabs are complete. The 6th floor concrete should be completed by 8/22. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of July 16th and July 23rd, 2018

At Site A the ground floor through 3rd floor slabs are complete. The 4th floor concrete should be completed by 8/3. The Con-Ed vaults are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of June 18th, June 25th, July 2nd, and July 9th, 2018

At Site A the ground floor through 3rd floor slabs are complete. The 4th floor concrete should be completed by 7/23. The Con-Ed vaults are installed on Kent Ave , the bike lane has been returned to the curb however ConEd … Continue reading

Posted in Construction Updates