Category Archives: Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of January 21st and January 28th, 2019

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Framing and rebar above the bridge has begun. We will be pouring the 28th floor slab the week of the 28th and frame … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of January 7th and January 14th, 2018

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Framing and rebar above the bridge has begun. This is a lengthy process and are expecting to pour the slabs at the end … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of December 24th and December 31st, 2018

At Site A the ground floor through 22th floor commercial and 28th floor Residential slabs are complete. Utility work in the street on Kent avenue  is mostly complete with gas work wrapping up in the spring. MEP trades will continue … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of December 10th and December 17th, 2018

At Site A the ground floor through 22th floor commercial and 27th floor Residential slabs are complete. Utility work in the street on Kent avenue  is mostly complete with gas work wrapping up in the spring. MEP trades will continue … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of November 26th and December 3rd, 2018

At Site A the ground floor through 20th floor commercial and 26th floor Residential slabs are complete. There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the coming few weeks. MEP trades will continue their … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of November 12th and November 19th, 2018

At Site A the ground floor through 18th floor commercial and 23th floor Residential slabs are complete. There will be water, sewer and finalizing of Con-Ed work on Kent avenue during the coming few weeks. Sidewalk shed is erected. MEP … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of October 29th and November 5th, 2018

At Site A the ground floor through 15th floor commercial and 20th floor Residential slabs are complete. The commercial 16, 17 & 18 and residential 21, 22 and 23rd floor slabs will be complete by 11/9 .  There will be … Continue reading

Posted in Construction Updates