DOMINO CONSTRUCTION UPDATE- WEEKS OF SEPTEMBER 29 AND OCTOBER 6
Excavation has commenced at Site B, with soil removal and foundation work underway. The site is fenced off on all streets. All sites at Domino, with the exception of site B, are now completed or have interior work only remaining. … Continue reading
Posted in Construction Updates