DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 5 AND FEBRUARY 12
Tower Crane has been erected and is active daily at Site D. Concrete
superstructure and steel erection is complete at the Refinery and all façade
masonry work is complete. Interior construction of the Refinery is underway and
glass installation is ongoing. Site B is fenced off and is used for
refinery construction staging. A separate portion of site B is accessible off
river street containing Domino Park bathrooms and staffing/operations. Construction of Domino Park, Site E and Site A is complete. All superstructure work at Site D is now complete. Tower facade
installation work is underway. Interior construction is underway within Site D.
Above grade work at site C has commenced.
Public entrances to Domino Park are on Grand St, South 1st St, and South 5th St.
Posted in Construction Updates