DOMINO CONSTRUCTION UPDATE:Week of November 10th, 2014 and November 17, 2014
Demolition activities concluded at the Raw Sugar Warehouse and Sorting, grading, and cleaning activities are ongoing at the Raw Sugar Warehouse.The structural steel frame along the East River remains to be used for the construction of an elevated public park. … Continue reading