DOMINO CONSTRUCTION UPDATE: Week of June 26th, 2017 and July 3rd, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fit out has begun. Final inspections throughout the building are scheduled in the next month.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of June 12th, 2017 and June 19th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fit out has begun. Final inspections throughout the building are scheduled in the next month.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of May 29th, 2017 and June 5th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is nearly complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fit out has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of May 15th, 2017 and May 22nd, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is nearly complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of May 1st, 2017 and May 8th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel is nearly complete and painting of the artifacts has begun.

The public park located on Site C is open 6 days a week.

At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 17th, 2017 and April 24th, 2017

Construction of our park has begun, including earthwork and the marine platform deck. Our precast bulkhead work is nearly complete. Relocation all the syrup tanks and gantry crane bases are completed. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical and plumbing work has begun.

The new bulkhead and seawall system is substantially complete, punchlist items remain. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is COMPLETE. All MEP trades are doing riser and horizontal work. Installation of CMU, exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 3rd, 2017 and April 10th, 2017

Construction of our park has begun, including earthwork and the marine platform deck. Our precast bulkhead work is nearly complete. Relocation all the syrup tanks and gantry crane bases are completed. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical and plumbing work has begun.

The new bulkhead and seawall system is substantially complete, punchlist items remain. The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is COMPLETE. All MEP trades are doing riser and horizontal work. Installation of CMU, exterior & interior framing and MEP work is ongoing. Exterior walls are being clad and waterproofed using the mast climber’s onsite. Mechanical rooms are being built out and apartment fitout has begun.

Please feel free to reach out us at domino@twotreesny.com with additional questions.

Posted in Construction Updates