DOMINO CONSTRUCTION UPDATE: Weeks of September 17th and September 24th, 2018

At Site A the ground floor through 10th floor slabs are complete. The 11th and 12th Floor concrete should be completed by 9/30. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be doing cable pulls equipment through September which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection has begun on a second shift and will end prior to 10pm every evening.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of September 3rd and September 10th, 2018

 

At Site A the ground floor through 8th floor slabs are complete. The 9th and 10th Floor concrete should be completed by 9/7. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be doing cable pulls equipment the beginning of September which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection has begun on a second shift and will end prior to 10pm every evening.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of August 20th and August 27th, 2018

At Site A the ground floor through 6th floor slabs are complete. The 7th and 8th Floor concrete should be completed by 9/7. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be doing cable pulls equipment the beginning of September which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection has begun on a second shift and will end prior to 10pm every evening.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street.

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of July 30th, August 6th and August 13th, 2018

At Site A the ground floor through 5th floor slabs are complete. The 6th floor concrete should be completed by 8/22. The Con-Ed vaults and transformers are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be doing cable pulls equipment later in August which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection is set to begin August 20th

 

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street

 

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of July 16th and July 23rd, 2018

At Site A the ground floor through 3rd floor slabs are complete. The 4th floor concrete should be completed by 8/3. The Con-Ed vaults are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be dropping equipment later in July (heat advisory(s) impact their availability) which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection is set to begin in August.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Site D has been partially paved over and the remainder of the site to River Street will get gravel. We intend to use this site for events/ flex space.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of June 18th, June 25th, July 2nd, and July 9th, 2018

At Site A the ground floor through 3rd floor slabs are complete. The 4th floor concrete should be completed by 7/23. The Con-Ed vaults are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will be dropping equipment later in July (heat advisory(s) impact their availability) which will disrupt the bike lane for a limited duration. Sidewalk shed is erected. MEP trades will continue their overhead and in deck work. Curtainwall erection is set to begin in August.

Construction of the Domino Park is complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Site D has been partially paved over and the remainder of the site to River Street will get gravel. We intend to use this site for events/ flex space.

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of May 28th, June 4th, and June 11th, 2018

At Site A the ground floor and 2nd floor slab are complete. The 3rd floor concrete should be completed by 6/22. The Con-Ed vaults will be installed on Kent Ave this will reroute bike and pedestrian traffic for 3-4 weeks. Sidewalk shed is erected. MEP trades have begun their overhead and in deck work. Curtainwall erection is set to begin in August.

Construction of the Domino Park is nearly complete. The park has opened and has entrances on Grand Street, South 3rd Street and South 5th Street

The public park located on Site C is open 6 days a week.

Site E construction is complete.

Posted in Construction Updates