DOMINO CONSTRUCTION UPDATE:Week of February 2nd, 2015 and February 9th, 2015
Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the site. Site E is imminently going to begin construction. Mobilization onsite and the construction fence will … Continue reading
Posted in Construction Updates