Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the site.
Site E is imminently going to begin construction. Mobilization onsite and the construction fence will begin on the 16th of February.