-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 16 AND FEBRUARY 23
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 2 AND FEBRUARY 9
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 19 AND JANUARY 26
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 5 AND JANUARY 12
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 22 AND DECEMBER 29
February 2015 M T W T F S S 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Daily Archives: February 11, 2015
DOMINO CONSTRUCTION UPDATE:Week of February 2nd, 2015 and February 9th, 2015
Asbestos abatement is ongoing inside the Boiler House stacks. Mechanical demolition will resume once abatement is complete. Sorting and grading activities are ongoing throughout the site. Site E is imminently going to begin construction. Mobilization onsite and the construction fence will … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE:Week of February 2nd, 2015 and February 9th, 2015