DOMINO CONSTRUCTION UPDATE:Week of March 16th, 2015 and March 23rd, 2015
Soot removal and asbestos abatement was completed in the Boiler House stacks. Mechanical demolition is still necessary to remove the standing skeleton of the building. Preparations for interior hand demolition of The Refinery building has begun. The removal of the … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE:Week of March 16th, 2015 and March 23rd, 2015