DOMINO CONSTRUCTION UPDATE:Week of March 30th, 2015 and April 6th, 2015
Mechanical demolition is ongoing to remove the standing skeleton of the boiler house building. hand demolition continues in The Refinery building. The removal of the Domino Sugar cranes along the East River is complete and the contractor is completely demobilized. … Continue reading