DOMINO CONSTRUCTION UPDATE:Week of May 11th, 2015 and May 18th, 2015

Hand demolition of steel beams is ongoing to remove the standing skeleton of the boiler house building, half of which has been completed. Hand demolition continues in The Refinery building.┬áThree (3) test-piles are installed on the Site. Fencing was installed … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of April 27th, 2015 and May 4th, 2015

Hand demolition of steel beams is ongoing to remove the standing skeleton of the boiler house building. The hand demolition in The Refinery building is continuing. At the north edge of the Site near South 1st Street, they have begun … Continue reading