DOMINO CONSTRUCTION UPDATE:Week of May 25th, 2015 and June 1st, 2015

The boiler house demolition is completed. Hand demolition in The Refinery Building continues. Installation of new hay bale erosion control fence is occurring. A contractor has mobilized a barge with crane to begin removal of bulkhead concrete decking on the north … Continue reading