DOMINO CONSTRUCTION UPDATE:Week of December 28th, 2015 and January 4th, 2015
These are slow weeks due to the Holiday, hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River. The … Continue reading
Posted in Construction Updates