DOMINO CONSTRUCTION UPDATE:Week of November 30th, 2015 and December 7th, 2015
Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River. The public park located on Site C is open … Continue reading
Posted in Construction Updates