-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 8 AND DECEMBER 15
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 24 AND DECEMBER 1
- DOMINO CONSTRUCTION UPDATE- WEEKS OF NOVEMBER 10 AND NOVEMBER 17
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 27 AND NOVEMBER 3
- DOMINO CONSTRUCTION UPDATE- WEEKS OF OCTOBER 13 AND OCTOBER 20
January 2016 M T W T F S S 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Monthly Archives: January 2016
DOMINO CONSTRUCTION UPDATE:Week of December 28th, 2015 and January 4th, 2015
These are slow weeks due to the Holiday, hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. they are continuing to remove metal piers from the River. The … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE:Week of December 28th, 2015 and January 4th, 2015