DOMINO CONSTRUCTION UPDATE:Week of April 18th, 2016 and April 25th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the 5th floor slab and supporting columns are being poured daily. All MEP trades have mobilized and have begun deck work and coordination efforts.