DOMINO CONSTRUCTION UPDATE:Week of June 13th, 2016 and June 20th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking.  The public park located on Site C is open 6 days a week.

At Site E, superstructure concrete is underway and sections of the 9th floor slab on the south tower and supporting columns are being poured daily. All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work has begun.

This entry was posted in Construction Updates. Bookmark the permalink.