-
Recent Posts
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 16 AND FEBRUARY 23
- DOMINO CONSTRUCTION UPDATE- WEEKS OF FEBRUARY 2 AND FEBRUARY 9
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 19 AND JANUARY 26
- DOMINO CONSTRUCTION UPDATE- WEEKS OF JANUARY 5 AND JANUARY 12
- DOMINO CONSTRUCTION UPDATE- WEEKS OF DECEMBER 22 AND DECEMBER 29
Daily Archives: October 9, 2016
DOMINO CONSTRUCTION UPDATE:Week of June 27th, 2016 and July 4th, 2016
Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE:Week of June 27th, 2016 and July 4th, 2016