DOMINO CONSTRUCTION UPDATE:Week of October 17th, 2016 and October 24th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is complete. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of October 3rd, 2016 and October 10th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is complete. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut … Continue reading

Posted in Construction Updates

DOMINO CONSTRUCTION UPDATE:Week of September 19th, 2016 and September 26th, 2016

Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is complete. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut … Continue reading