DOMINO CONSTRUCTION UPDATE: Week of January 9th, 2017 and January 16th, 2017
The removal of the bulkhead concrete decking on the river front is complete. New piers are being installed in the east river to support the future bulkhead decking. Piers are being cut to final heights and pile caps are being … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Week of January 9th, 2017 and January 16th, 2017