DOMINO CONSTRUCTION UPDATE: Week of June 12th, 2017 and June 19th, 2017

Construction of the Domino Park is ongoing, including earthwork and utility work. Our bulkhead piers and deck is complete. Layout and construction of CMU planter walls and the western perimeter wall has begun. Electrical, utility and plumbing work has begun. The elevated walk steel … Continue reading