Construction of the Domino Park is ongoing, including earthwork, utility work, and concrete. Layout and construction of CMU planter walls is nearly complete and the western perimeter wall has begun. Electrical, Mechanical and plumbing work is ongoing. The elevated walk steel is complete and painting of the artifacts has begun. We are expecting pavers and precast plank work to be delivered by the end of September. Work is progressing from the north to the southern end of the site.
The public park located on Site C is open 6 days a week.
At Site E, All MEP trades are doing riser and horizontal work along with roughing and final installation. Installation of exterior cladding & interior framing and MEP work is ongoing. Exterior walls are mostly complete with the remaining being clad and waterproofed using the mast climber’s at the north side of the building. Mechanical rooms are mostly completed and apartment fit out is ongoing. Final inspections throughout the building are completed for the first TCO. Inspections for future TCOs are to be scheduled. The sidewalk on Kent Avenue is open to the public.
At Site A Excavation, SOE and dewatering work has begun. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun.