DOMINO CONSTRUCTION UPDATE: Weeks of June 18th, June 25th, July 2nd, and July 9th, 2018
At Site A the ground floor through 3rd floor slabs are complete. The 4th floor concrete should be completed by 7/23. The Con-Ed vaults are installed on Kent Ave , the bike lane has been returned to the curb however ConEd … Continue reading