DOMINO CONSTRUCTION UPDATE: Weeks of July 16th and July 23rd, 2018

At Site A the ground floor through 3rd floor slabs are complete. The 4th floor concrete should be completed by 8/3. The Con-Ed vaults are installed on Kent Ave , the bike lane has been returned to the curb however ConEd will … Continue reading