DOMINO CONSTRUCTION UPDATE: Weeks of October 15th and October 22nd, 2018
At Site A the ground floor through 13th floor commercial and 16th floor Residential slabs are complete. The commercial 14 &15 and residential 17, 18 and 19th floor slabs will be complete by 10/26 . There will be water, sewer … Continue reading
Posted in Construction Updates
Comments Off on DOMINO CONSTRUCTION UPDATE: Weeks of October 15th and October 22nd, 2018